How to control a construction project budget

Last reviewed: 2026-10-25

In short

Set a budget for each expense category of a project, approve it, and track used = spent + committed against it. The status is OK under 80%, Warning from 80% to 100% and Over above 100%, so the warning arrives while there is still money left.

Setting the budget

Budgets are per expense category, main or sub, one line per category per project.

  • The budget is approved, recording who approved it and when.
  • Every later change is a revision with the previous amount, the new amount, the reason, who and when.
  • A main category without its own line takes the sum of its sub-categories.

Spent and committed

Two figures matter besides the budget itself.

  • Spent: everything paid out on the project, excluding voided lines.
  • Committed: approved contractor work that has not been paid yet.
  • Cheques written but not cashed are not counted as committed, to avoid counting them twice.

Reading the status

Used is spent plus committed, compared with the current budget.

  • OK: under 80%.
  • Warning: 80% to 100%.
  • Over: above 100%.
  • Unbudgeted: spending where no budget exists for the category.

Common questions

What counts as committed?
Approved contractor work that has not been paid. Uncashed cheques are not counted.
Can a budget change after approval?
Yes, as a recorded revision with the reason, who and when. The original amount stays on record.
Where do I see profit?
The profit report shows realized and expected profit, committed cost and budget for every project.

See it on your own projects

Ask for a demo and we will walk through this with your cheques, custodies and contractors.

Request a demo

Related guides